A thirty-four-square-metre living room, bright from floor to ceiling
Large-format marble-look porcelain, a false ceiling with a cornice, recessed lighting and a new aluminium balcony door: the living room of a flat in Hydra, redone before a wedding.
- Town
- Hydra
- Kind
- Flats
- Area
- 34 m²
- Length of the works
- 12 working days
- Budget
- 1 320 000 DAindicative, materials and labour


Before the works
30 × 30 tiles cracked on the diagonal, paint peeling in sheets, cables stapled across the ceiling and an old timber balcony door that let in the wind and the dust. The room looked smaller than it is.
What was done
Works opened with the electrics: the exposed cables disappeared into concealed conduit, the sockets were doubled and a new lighting circuit was prepared for the false ceiling. The plasterer then hung the plasterboard ceiling with a cornice all round.
The 60 × 120 Carrara-look porcelain went down in flexible adhesive over the old tiles, once the flatness was checked, with 2 mm spacers and levelling clips so the large tiles do not lip. Matching skirting was cut from the same tiles.
The walls took a skim coat, a primer and two coats of stone-coloured matt. The aluminium balcony door was fitted as a renovation frame over the old one, without breaking the sill.
The steps
| Room | Step | Starts | Takes | Works schedule, in working days from Saturday to Thursday |
|---|---|---|---|---|
| Site | Site protection | day 1 | 1 d | |
| Living room | Electrics | day 2 | 1 d | |
| Living room | Plaster and false ceiling | day 3 | 3 d | |
| Living room | Flooring | day 6 | 3 d | |
| Living room | Painting | day 9 | 3 d | |
| Site | Cleaning and handover | day 12 | 1 d |
The products used
All of them from the Qarmoud catalogue and our depots.
- Veined white marble-look porcelain 60 × 120 polishedTiles & wall tiles
- Flexible large-format adhesive C2TE S1 — 25 kgTiles & wall tiles
- Porcelain skirting 60 × 8 cmTiles & wall tiles
- Plasterboard BA13 standard 1.20 × 2.50 mPlaster & partitions
- Moulded plaster cornice — 2 mPlaster & partitions
- 7 W warm-white LED downlightElectrical
- Acrylic primer-undercoat — 15 L bucketPaint
- Matt acrylic paint — 15 L bucketPaint
- Aluminium sliding patio door 200 × 215Doors & windows
The team
- Asma BenamaraInterior designer, Qarmoud AtelierFictional character
- Adel MekhalfaRenovation project manager, Qarmoud AtelierFictional character
- Abdelkader GhezaliSite foremanFictional character
Other jobs

Kitchens — Draria
An eleven-square-metre kitchen that finally works
- Area
- 11 m²
- Length
- 12 working days
- Budget
- 1 150 000 DA

Bathrooms — Bab Ezzouar
Six square metres, a walk-in shower and green zellige
- Area
- 6 m²
- Length
- 14 working days
- Budget
- 780 000 DA

Roof terraces and waterproofing — Blida
A roof terrace redone before the autumn rains
- Area
- 96 m²
- Length
- 8 working days
- Budget
- 690 000 DA

Villas — Kouba
A white lime façade with blue shutters, as it should be
- Area
- 180 m²
- Length
- 21 working days
- Budget
- 1 480 000 DA

Shops and offices — El Biar
A shop in El Biar that opened on the day announced
- Area
- 62 m²
- Length
- 14 working days
- Budget
- 2 100 000 DA

Villas — Chéraga
A villa in Chéraga renovated from the roof terrace to the heating
- Area
- 210 m²
- Length
- 14 working days
- Budget
- 9 800 000 DA