I’m building my house

From the plot to the keys, one storey after another. For each phase: what happens on site, what to buy, and what the materials cost, as a range.

Typical house: ground floor plus one, 110 m² a storey.

Go to the savings plan
Step 1: the foundations and rebar starter bars on the plot.

Plot and building permit

  1. Phase 1 of 7

    Plot and building permit

    What happens

    The plot is marked out, a licensed architect draws the plans and the building permit goes to the town hall. A soil survey says what the house will stand on.

    What to buy

    • Setting-out pegs and line
    • A laser level for the levels
    Materials, indicative rangeNo materials to buy at this phase.
  2. Phase 2 of 7

    Foundations

    What happens

    The trenches are dug and the blinding poured, then the footings and ground beams are reinforced and concreted. A block plinth rises to the ground slab.

    What to buy

    • Cement, river sand and gravel
    • HA12 and HA8 rebar, tying wire
    • 20 cm blocks for the plinth
    Materials, indicative range680 000 – 1 100 000 DZDindicative
  3. Phase 3 of 7

    Frame and structural work

    What happens

    Storey by storey: columns and beams poured, the hollow-block floor laid on its joists, ring beams, then red brick infill course by course. Starter bars wait for the next storey.

    What to buy

    • Cement, sand, gravel, rebar
    • Hollow blocks and prestressed joists
    • 12- and 8-hole bricks, mortar
    Materials, indicative range2 230 000 – 2 990 000 DZDindicative
  4. Phase 4 of 7

    Roof terrace and waterproofing

    What happens

    On the top slab: the screed to falls, the primer, the bitumen membrane with its upstands against the parapet, insulation, then terrace tiles as protection.

    What to buy

    • Primer and SBS membranes
    • Extruded polystyrene
    • Terrace tiles, adhesive and grout
    Materials, indicative range430 000 – 540 000 DZDindicative
  5. Phase 5 of 7

    Services and plastering

    What happens

    Services go in before plaster: plumbing, gas, electrics, then gypsum plaster on the walls and light partitions in plasterboard.

    What to buy

    • BA13 boards, tracks, studs and joint compound
    • Pipes, fittings and cable from the counter
    • Building plaster
    Materials, indicative range100 000 – 320 000 DZDindicative
  6. Phase 6 of 7

    Finishes

    What happens

    Floor tiles, wall tiles in the wet rooms, paint, inside and outside joinery, sanitaryware and the kitchen.

    What to buy

    • Tiles, wall tiles, adhesive, grout, skirting
    • Primer and paint
    • Doors, windows, sanitaryware
    Materials, indicative range490 000 – 1 050 000 DZDindicative
  7. Phase 7 of 7

    Handing over the keys

    What happens

    The last snags are closed, the meters fitted, the certificate of conformity requested. The family moves in — and the next storey’s starter bars are already waiting.

    What to buy

    • Nothing to buy: the snag list, and the warranty on what was fitted
    Materials, indicative rangeNo materials to buy at this phase.

What the ranges count

  • A ground-plus-one house of 110 m² a storey on a flat plot, with a hollow-block floor 16 + 4 (blocks and joists).
  • Concrete at 350 kg/m³: 0.22 to 0.30 m³ per m² of floor, 80 to 100 kg of steel per m³; foundations at 0.20 to 0.30 m³ per m².
  • Double brick façades (12- and 8-hole), 18 % openings; inside partitions in 8-hole brick.
  • Finishes: tiles over 85 % of the floor, wall tiles in the kitchen and bathroom, two coats of paint.
  • Today’s catalogue prices, tax included. No labour, plumbing, electrics, joinery or permit fees: these are materials ranges, not a quote.

The savings plan, storey by storey

Many families build one storey every year or two. Say how much you put aside each month: the plan shows when each storey can start, with its materials budget.

Saïd and Fatiha Mebarki plan their next floor with Amel (fictional characters).
Saïd and Fatiha Mebarki plan their second floor (fictional characters).
m²
Storeys planned in all
Storeys already built
DA
DA

Timeline by storey

  1. Ground floorAlready built
  2. First floorAlready built
  3. Second floorNext storey
    Materials
    1 560 000 – 2 030 000 DZD
    Saving target
    2 030 000 DZD
    Can start
    October 2027
    Works end
    February 2028

The saving target is the top of the range, to be safe.