A white lime façade with blue shutters, as it should be
A hundred and eighty square metres of façade on a house in Kouba: failed render hacked off, bricks repaired, lime render, aluminium windows and blue shutters.
- Town
- Kouba
- Kind
- Villas
- Area
- 180 m²
- Length of the works
- 21 working days
- Budget
- 1 480 000 DAindicative, materials and labour


Before the works
A cracked cement render that sounded hollow, bare brick under the window sills, rusty metal shutters stuck half open and black streaks under every balcony.
What was done
A scaffold went up on the street side with a safety net for passers-by. All the render that sounded hollow was hacked off, broken bricks replaced and the cracks treated before a single coat.
The render was redone in hydraulic lime, in two passes, with a waterproofer in the body coat: lime lets the wall dry out and does not crack the way the old, over-stiff cement render did.
The windows were replaced with aluminium sliders and the rusty shutters with blue aluminium louvres. A stabiliser and two coats of white façade paint finished the job.
The steps
| Room | Step | Starts | Takes | Works schedule, in working days from Saturday to Thursday |
|---|---|---|---|---|
| Villas | Scaffolding and protection | day 1 | 2 d | |
| Villas | Hacking off the failed render | day 3 | 4 d | |
| Villas | Crack and brick repairs | day 7 | 2 d | |
| Villas | Lime render in two passes | day 9 | 6 d | |
| Villas | Aluminium windows and shutters | day 15 | 3 d | |
| Villas | Façade paint | day 18 | 4 d |
The products used
All of them from the Qarmoud catalogue and our depots.
- Natural hydraulic lime — 25 kgStructural materials
- Fine sand 0/2 for render — m³Structural materials
- Integral waterproofer — 5 LStructural materials
- Stabilising solution — 5 LPaint
- Siloxane acrylic masonry paint — 15 L bucketPaint
- Aluminium 2-pane sliding window 120 × 100Doors & windows
- Aluminium louvred shutters 100 × 120Doors & windows
The team
- Adel MekhalfaRenovation project manager, Qarmoud AtelierFictional character
- Abdelkader GhezaliSite foremanFictional character
Other jobs

Kitchens — Draria
An eleven-square-metre kitchen that finally works
- Area
- 11 m²
- Length
- 12 working days
- Budget
- 1 150 000 DA

Bathrooms — Bab Ezzouar
Six square metres, a walk-in shower and green zellige
- Area
- 6 m²
- Length
- 14 working days
- Budget
- 780 000 DA

Flats — Hydra
A thirty-four-square-metre living room, bright from floor to ceiling
- Area
- 34 m²
- Length
- 12 working days
- Budget
- 1 320 000 DA

Roof terraces and waterproofing — Blida
A roof terrace redone before the autumn rains
- Area
- 96 m²
- Length
- 8 working days
- Budget
- 690 000 DA

Shops and offices — El Biar
A shop in El Biar that opened on the day announced
- Area
- 62 m²
- Length
- 14 working days
- Budget
- 2 100 000 DA

Villas — Chéraga
A villa in Chéraga renovated from the roof terrace to the heating
- Area
- 210 m²
- Length
- 14 working days
- Budget
- 9 800 000 DA